Maine

Portland Airport's Main Runway Shut Down for $13.7M Project

The 56-day closure required flight operations to shift to a secondary runway on Monday

NECN

The main runway at Portland International Jetport closed Monday for a $13.7 million project that involves repaving and installation of new LED lighting.

The 56-day closure required flight operations to shift to a secondary runway on Monday, causing a change in air traffic patterns over Portland, South Portland, Scarborough and Westbrook, officials said.

The airport’s instrument landing system will be down, which could lead to flight delays or cancellations in times of low visibility, officials said.

The period when the intersection between the two runways is repaved from May 16 to June 13 will result in reduced hours of operation, with no flights after 10:30 p.m. and 5:45 a.m.

Officials previously told NECN that some 5,000 flights will be affected to some degree by these changes, but cancellations and significant delays are not expected.

Workers have begun the process of removing electrical components and removing runway asphalt.

Copyright AP - Associated Press