    MBTA Red Line Repairs Complete

    It's been a long summer for the MBTA Red Line since one train derailed in June. After months of repair, the JFK/UMass Station is ready to reopen to the public. (Published Thursday, Sept. 26, 2019)

    The MBTA says its new Orange Line trains are temporarily out of service due to a door malfunction, even as regular service has resumed on the Red Line following months of repairs. 

    The MBTA said Wednesday the new trains were taken out of service after a set of doors opened as one of the trains traveled near Massachusetts Avenue Station Friday. The agency said a component called a bump stop did not function properly, leading to the malfunction.

    The faulty components were being replaced, and the trains were expected to be back in service by Monday, the agency said. 

    The issues come six weeks after the MBTA rolled out six new Orange Line trains as part of a plan to replace the line's 152 trains over the next two years.   

    MBTA Says Broken Axle Caused Red Line Derailment

    [NECN] MBTA Says Broken Axle Caused Red Line Derailment

    Following an extensive investigation, MBTA officials now say a broken axle is to blame for a derailment on the Red Line back in June.

    (Published Monday, Sept. 16, 2019)

    They also come as regular service has resumed on the Red Line, three months after a derailment caused significant damage and massive delays. 

    MBTA officials said Wednesday the signal system between JFK/UMass and North Quincy was repaired over the weekend and that crews had finished testing it.

    When the train derailed June 11 near the JFK/UMass station in Boston's Dorchester neighborhood, three signal bungalows which housed track switches had to be repaired. Twenty miles of signal cable also had to be replaced.

    Due to the repairs, the MBTA was forced to run trains at reduced speeds along stretches of the track, which caused delays for commuters.

    Following an extensive investigation, MBTA officials said last week a broken axle was to blame for the derailment.

    The work had originally been expected to be completed by Labor Day but was pushed back to mid-October.

    Meeting Could Reveal Cause of Red Line Derailment

    [NECN] Meeting Could Reveal Cause of Red Line Derailment

    After more than three months, we could finally learn what caused an MBTA Red Line train to derail in June.

    (Published Monday, Sept. 16, 2019)

    Get the latest from necn anywhere, anytime

    • Download the App

      Available for IOS and Android